Construction Updates – Week of 01/25/2019
Week of 01/25/2019
SCHEDULE UPDATE:
Even though weather has not been cooperating, we have been able to level the area where the construction and marketing trailers will be set. The construction entrance from the main street has also been installed.
DEVELOPMENT UPDATE
PROJECTED CO: TBD
PROGRESS NOTES BY TRADE:
- Earthwork – Weather permitting, the construction and marketing trailers will be placed next week. The excavators have staked the land and are ready to move dirt once the ground dries up from the heavy rains. They will be grading out the berm section as well.
Construction Photos 01/25/2019